Plumas County -- Caltrans is progressing construction operations on the A-13 at State Route (SR) 36 Safety Project, near Chester from just west of Bailey Creek Bridge to just east of County Road A-13 in Plumas County. The safety project includes the construction of a traffic circle (roundabout). Constructing the roundabout includes removing the existing asphalt, performing earthwork cuts, placing asphalt concrete structural sections in the circulatory roadway and approach legs, and adding concrete curbing for the roundabout and approach legs. In addition, the safety project will relocate one utility pole, add striping and new landscaping, add luminaries on the approach legs, and install new signage.
Motorists will encounter one-way traffic control with up to 20 minute delays, 24 hours a day/7 days a week for the foreseeable future, to expedite project completion.
4th of July Holiday:
Caltrans are asking motorists to please avoid the Plumas County Road A-13 at State Route 36 intersection, as 24-hour traffic control will continue through the 4th of July holiday. Delays of 20 minutes or more are expected with incoming heavy traffic. Delays are expected to increase significantly for the holiday, with heavy traffic accessing scheduled holiday events.
Motorists are encouraged to navigate the peninsula area from the east on SR 147, and then onto Plumas County Road A-13 going north. Parade access is available from SR 89 north to SR 36 east.
Please allot extra time for delays and slow down and drive carefully in and around the project area.
The construction project includes 85 working days, and is expected to be completed by the end of September, pending weather and operations.
Knife River Construction, North Region Construction and Caltrans District 2 thank the traveling public and local communities for their patience during the construction of the project. Construction projects are subject to changes without prior notice. Caltrans and its contractors do our best to keep the public informed.
For more information about transportation and other infrastructure projects funded with state and federal investments, visit RebuildingCA.ca.gov and Build.gov.ca.
###
To stay up to date on highway projects, please follow us on Facebook and Twitter. Project information can also be found on the District 2 webpage. The public can also call (530) 225-3426 during working hours or send an email to [email protected]. Updated highway conditions for California can be found on QuickMap and on One-Stop-Shop for the Western U.S.
Caltrans District 2 - PIO office | 1657 Riverside Drive | Redding, CA 96001 US
Unsubscribe | Update Profile | Constant Contact Data Notice
A-13 at Route 36 Project
in Plumas County in 24/7 Traffic Control
Plumas County -- Caltrans is progressing construction operations on the A-13 at State Route (SR) 36 Safety Project, near Chester from just west of Bailey Creek Bridge to just east of County Road A-13 in Plumas County. The safety project includes the construction of a traffic circle (roundabout). Constructing the roundabout includes removing the existing asphalt, performing earthwork cuts, placing asphalt concrete structural sections in the circulatory roadway and approach legs, and adding concrete curbing for the roundabout and approach legs. In addition, the safety project will relocate one utility pole, add striping and new landscaping, add luminaries on the approach legs, and install new signage.
Motorists will encounter one-way traffic control with up to 20 minute delays, 24 hours a day/7 days a week for the foreseeable future, to expedite project completion.
4th of July Holiday:
Caltrans are asking motorists to please avoid the Plumas County Road A-13 at State Route 36 intersection, as 24-hour traffic control will continue through the 4th of July holiday. Delays of 20 minutes or more are expected with incoming heavy traffic. Delays are expected to increase significantly for the holiday, with heavy traffic accessing scheduled holiday events.
Motorists are encouraged to navigate the peninsula area from the east on SR 147, and then onto Plumas County Road A-13 going north. Parade access is available from SR 89 north to SR 36 east.
Please allot extra time for delays and slow down and drive carefully in and around the project area.
The construction project includes 85 working days, and is expected to be completed by the end of September, pending weather and operations.
Knife River Construction, North Region Construction and Caltrans District 2 thank the traveling public and local communities for their patience during the construction of the project. Construction projects are subject to changes without prior notice. Caltrans and its contractors do our best to keep the public informed.
For more information about transportation and other infrastructure projects funded with state and federal investments, visit RebuildingCA.ca.gov and Build.gov.ca.
A-13 at Route 36 Project
in Plumas County in 24/7 Traffic Control
Plumas County -- Caltrans is progressing construction operations on the A-13 at State Route (SR) 36 Safety Project, near Chester from just west of Bailey Creek Bridge to just east of County Road A-13 in Plumas County. The safety project includes the construction of a traffic circle (roundabout). Constructing the roundabout includes removing the existing asphalt, performing earthwork cuts, placing asphalt concrete structural sections in the circulatory roadway and approach legs, and adding concrete curbing for the roundabout and approach legs. In addition, the safety project will relocate one utility pole, add striping and new landscaping, add luminaries on the approach legs, and install new signage.
Motorists will encounter one-way traffic control with up to 20 minute delays, 24 hours a day/7 days a week for the foreseeable future, to expedite project completion.
4th of July Holiday:
Caltrans are asking motorists to please avoid the Plumas County Road A-13 at State Route 36 intersection, as 24-hour traffic control will continue through the 4th of July holiday. Delays of 20 minutes or more are expected with incoming heavy traffic. Delays are expected to increase significantly for the holiday, with heavy traffic accessing scheduled holiday events.
Motorists are encouraged to navigate the peninsula area from the east on SR 147, and then onto Plumas County Road A-13 going north. Parade access is available from SR 89 north to SR 36 east.
Please allot extra time for delays and slow down and drive carefully in and around the project area.
The construction project includes 85 working days, and is expected to be completed by the end of September, pending weather and operations.
Knife River Construction, North Region Construction and Caltrans District 2 thank the traveling public and local communities for their patience during the construction of the project. Construction projects are subject to changes without prior notice. Caltrans and its contractors do our best to keep the public informed.